 Accounting Standard (AS) 7 *

(revised 2002)

Construction Contracts #

[This Accounting Standard includes paragraphs set in bold italic type and plain type, which have equal authority. Paragraphs in bold italic type indicate the main principles. This Accounting Standard should be read in the context of its objective, the Preface to the Statements of Accounting Standards1 and the ‘Applicability of Accounting Standards to Various Entities’ (See Appendix 1 to this Compendium).]

Objective

The objective of this Standard is to prescribe the accounting treatment of revenue and costs associated with construction contracts. Because of the nature of the activity undertaken in construction contracts, the date at which the contract activity is entered into and the date when the activity is completed usually fall into different accounting periods. Therefore, the primary issue in accounting for construction contracts is the allocation of contract revenue and contract costs to the accounting periods in which construction work is performed. This Standard uses the recognition criteria established in the Framework for the Preparation and Presentation of Financial Statements to determine when contract revenue and contract costs should be recognised as revenue and expenses in the statement of profit and loss. It also provides practical guidance on the application of these criteria.

Scope

1 This Standard should be applied in accounting for construction contracts in the financial statements of contractors.

Definitions

2 The following terms are used in this Standard with the meanings specified:

 2.1 A construction contract is a contract specifically negotiated for the construction of an asset or a combination of assets that are closely interrelated or interdependent in terms of their design, technology and function or their ultimate purpose or use.

 2.2 A fixed price contract is a construction contract in which the contractor agrees to a fixed contract price, or a fixed rate per unit of output, which in some cases is subject to cost escalation clauses.

 2.3 A cost plus contract is a construction contract in which the contractor is reimbursed for allowable or otherwise defined costs, plus percentage of these costs or a fixed fee.

3 A construction contract may be negotiated for the construction of a single asset such as a bridge, building, dam, pipeline, road, ship or tunnel. A construction contract may also deal with the construction of a number of assets which are closely interrelated or interdependent in terms of their design, technology and function or their ultimate purpose or use; examples of such contracts include those for the construction of refineries and other complex pieces of plant or equipment.

4 For the purposes of this Standard, construction contracts include:

5 Construction contracts are formulated in a number of ways which, for the purposes of this Standard, are classified as fixed price contracts and cost plus contracts. Some construction contracts may contain characteristics of both a fixed price contract and a cost plus contract, for example, in the case of a cost plus contract with an agreed maximum price. In such circumstances, a contractor needs to consider all the conditions in paragraphs 22 and 23 in order to determine when to recognise contract revenue and expenses.

Combining and Segmenting Construction Contracts

6 The requirements of this Standard are usually applied separately to each construction contract. However, in certain circumstances, it is necessary to apply the Standard to the separately identifiable components of a single contract or to a group of contracts together in order to reflect the substance of a contract or a group of contracts.

7 When a contract covers a number of assets, the construction of each asset should be treated as a separate construction contract when:

8 A group of contracts, whether with a single customer or with several customers, should be treated as a single construction contract when:

9 A contract may provide for the construction of an additional asset at the option of the customer or may be amended to include the construction of an additional asset. The construction of the additional asset should be treated as a separate construction contract when:

Contract Revenue

10  Contract revenue should comprise:

11 Contract revenue is measured at the consideration received or receivable. The measurement of contract revenue is affected by a variety of uncertainties that depend on the outcome of future events. The estimates often need to be revised as events occur and uncertainties are resolved. Therefore, the amount of contract revenue may increase or decrease from one period to the next. For example:

12 A variation is an instruction by the customer for a change in the scope of the work to be performed under the contract. A variation may lead to an increase or a decrease in contract revenue. Examples of variations are changes in the specifications or design of the asset and changes in the duration of the contract. A variation is included in contract revenue when:

13 A claim is an amount that the contractor seeks to collect from the customer or another party as reimbursement for costs not included in the contract price. A claim may arise from, for example, customer caused delays, errors in specifications or design, and disputed variations in contract work. The measurement of the amounts of revenue arising from claims is subject to a high level of uncertainty and often depends on the outcome of negotiations. Therefore, claims are only included in contract revenue when:

14 Incentive payments are additional amounts payable to the contractor if specified performance standards are met or exceeded. For example, a contract may allow for an incentive payment to the contractor for early completion of the contract. Incentive payments are included in contract revenue when:

Contract Costs

 15 Contract costs should comprise:

16 Costs that relate directly to a specific contract include:

These costs may be reduced by any incidental income that is not included in contract revenue, for example, income from the sale of surplus materials and the disposal of plant and equipment at the end of the contract.

17 Costs that may be attributable to contract activity in general and can be allocated to specific contracts include:

Such costs are allocated using methods that are systematic and rational and are applied consistently to all costs having similar characteristics. The allocation is based on the normal level of construction activity. Construction overheads include costs such as the preparation and processing of construction personnel payroll. Costs that may be attributable to contract activity in general and can be allocated to specific contracts also include borrowing costs as per Accounting Standard (AS) 16, Borrowing Costs.

18 Costs that are specifically chargeable to the customer under the terms of the contract may include some general administration costs and development costs for which reimbursement is specified in the terms of the contract.

19 Costs that cannot be attributed to contract activity or cannot be allocated to a contract are excluded from the costs of a construction contract. Such costs include:

20 Contract costs include the costs attributable to a contract for the period from the date of securing the contract to the final completion of the contract. However, costs that relate directly to a contract and which are incurred in securing the contract are also included as part of the contract costs if they can be separately identified and measured reliably and it is probable that the contract will be obtained. When costs incurred in securing a contract are recognised as an expense in the period in which they are incurred, they are not included in contract costs when the contract is obtained in a subsequent period.

Recognition of Contract Revenue and Expenses

 21 When the outcome of a construction contract can be estimated reliably, contract revenue and contract costs associated with the construction contract should be recognised as revenue and expenses respectively by reference to the stage of completion of the contract activity at the reporting date. An expected loss on the construction contract should be recognised as an expense immediately in accordance with paragraph 35.

 22 In the case of a fixed price contract, the outcome of a construction contract can be estimated reliably when all the following conditions are satisfied:

 23 In the case of a cost plus contract, the outcome of a construction contract can be estimated reliably when all the following conditions are satisfied:

24 The recognition of revenue and expenses by reference to the stage of completion of a contract is often referred to as the percentage of completion method. Under this method, contract revenue is matched with the contract costs incurred in reaching the stage of completion, resulting in the reporting of revenue, expenses and profit which can be attributed to the proportion of work completed. This method provides useful information on the extent of contract activity and performance during a period.

25 Under the percentage of completion method, contract revenue is recognised as revenue in the statement of profit and loss in the accounting periods in which the work is performed. Contract costs are usually recognised as an expense in the statement of profit and loss in the accounting periods in which the work to which they relate is performed. However, any expected excess of total contract costs over total contract revenue for the contract is recognised as an expense immediately in accordance with paragraph 35.

26 A contractor may have incurred contract costs that relate to future activity on the contract. Such contract costs are recognised as an asset provided it is probable that they will be recovered. Such costs represent an amount due from the customer and are often classified as contract work in progress.

27 When an uncertainty arises about the collectability of an amount already included in contract revenue, and already recognised in the statement of profit and loss, the uncollectable amount or the amount in respect of which recovery has ceased to be probable is recognised as an expense rather than as an adjustment of the amount of contract revenue.

28 An enterprise is generally able to make reliable estimates after it has agreed to a contract which establishes:

It is also usually necessary for the enterprise to have an effective internal financial budgeting and reporting system. The enterprise reviews and, when necessary, revises the estimates of contract revenue and contract costs as the contract progresses. The need for such revisions does not necessarily indicate that the outcome of the contract cannot be estimated reliably.

29 The stage of completion of a contract may be determined in a variety of ways. The enterprise uses the method that measures reliably the work performed. Depending on the nature of the contract, the methods may include:

Progress payments and advances received from customers may not necessarily reflect the work performed.

30 When the stage of completion is determined by reference to the contract costs incurred upto the reporting date, only those contract costs that reflect work performed are included in costs incurred upto the reporting date. Examples of contract costs which are excluded are:

 31 When the outcome of a construction contract cannot be estimated reliably:

An expected loss on the construction contract should be recognised as an expense immediately in accordance with paragraph 35.

32 During the early stages of a contract it is often the case that the outcome of the contract cannot be estimated reliably. Nevertheless, it may be probable that the enterprise will recover the contract costs incurred. Therefore, contract revenue is recognised only to the extent of costs incurred that are expected to be recovered. As the outcome of the contract cannot be estimated reliably, no profit is recognised. However, even though the outcome of the contract cannot be estimated reliably, it may be probable that total contract costs will exceed total contract revenue. In such cases, any expected excess of total contract costs over total contract revenue for the contract is recognised as an expense immediately in accordance with paragraph 35.

33 Contract costs recovery of which is not probable are recognised as an expense immediately. Examples of circumstances in which the recoverability of contract costs incurred may not be probable and in which contract costs may, therefore, need to be recognised as an expense immediately include contracts:

34 When the uncertainties that prevented the outcome of the contract being estimated reliably no longer exist, revenue and expenses associated with the construction contract should be recognised in accordance with paragraph 21 rather than in accordance with paragraph 31.

Recognition of Expected Losses

 35 When it is probable that total contract costs will exceed total contract revenue, the expected loss should be recognised as an expense immediately.

36 The amount of such a loss is determined irrespective of:

Changes in Estimates

37 The percentage of completion method is applied on a cumulative basis in each accounting period to the current estimates of contract revenue and contract costs. Therefore, the effect of a change in the estimate of contract revenue or contract costs, or the effect of a change in the estimate of the outcome of a contract, is accounted for as a change in accounting estimate (see Accounting Standard (AS) 5, Net Profit or Loss for the Period, Prior Period Items and Changes in Accounting Policies). The changed estimates are used in determination of the amount of revenue and expenses recognised in the statement of profit and loss in the period in which the change is made and in subsequent periods.

Disclosure

38 An enterprise should disclose:

39 An enterprise should disclose the following for contracts in progress at the reporting date:

40. Retentions are amounts of progress billings which are not paid until the satisfaction of conditions specified in the contract for the payment of such amounts or until defects have been rectified. Progress billings are amounts billed for work performed on a contract whether or not they have been paid by the customer. Advances are amounts received by the contractor before the related work is performed.

41 An enterprise should present:

42 The gross amount due from customers for contract work is the net amount of:

for all contracts in progress for which costs incurred plus recognised profits (less recognised losses) exceeds progress billings.

43 The gross amount due to customers for contract work is the net amount of:

for all contracts in progress for which progress billings exceed costs incurred plus recognised profits (less recognised losses).

44 An enterprise discloses any contingencies in accordance with Accounting Standard (AS) 4, Contingencies and Events Occurring After the Balance Sheet Date2. Contingencies may arise from such items as warranty costs, penalties or possible losses.

Illustration

This illustration does not form part of the Accounting Standard. Its purpose is to illustrate the application of the Accounting Standard to assist in clarifying its meaning.

Disclosure of Accounting Policies

The following are illustrations of accounting policy disclosures:

Revenue from fixed price construction contracts is recognised on the percentage of completion method, measured by reference to the percentage of labour hours incurred upto the reporting date to estimated total labour hours for each contract.

Revenue from cost plus contracts is recognised by reference to the recoverable costs incurred during the period plus the fee earned, measured by the proportion that costs incurred upto the reporting date bear to the estimated total costs of the contract.

The Determination of Contract Revenue and Expenses

The following illustration illustrates one method of determining the stage of completion of a contract and the timing of the recognition of contract revenue and expenses (see paragraphs 21 to 34 of the Standard). (Amounts shown herein below are in Rs. lakhs)

A construction contractor has a fixed price contract for Rs. 9,000 to build a bridge. The initial amount of revenue agreed in the contract is Rs. 9,000. The contractor’s initial estimate of contract costs is Rs. 8,000. It will take 3 years to build the bridge.

By the end of year 1, the contractor’s estimate of contract costs has increased to Rs. 8,050.

In year 2, the customer approves a variation resulting in an increase in contract revenue of Rs. 200 and estimated additional contract costs of Rs. 150. At the end of year 2, costs incurred include Rs. 100 for standard materials stored at the site to be used in year 3 to complete the project.

The contractor determines the stage of completion of the contract by calculating the proportion that contract costs incurred for work performed upto the reporting date bear to the latest estimated total contract costs. A summary of the financial data during the construction period is as follows:

(amount in Rs. lakhs)

  Year 1 Year 2 Year 3
Initial amount of revenue agreed in contract 9,000 9,000 9,000
Variation - 200 200
Total contract revenue 9,000 9,000 9,000
Contract costs incurred upto the reporting date 2,093 6,168 8,200
Contract costs to complete 5,957 2,032 -
Total estimated contract cost 8,050 8,200 8,200
Estimated Profit 950 1,000 1,000
Stage of completion 26% 74% 100%

The stage of completion for year 2 (74%) is determined by excluding from contract costs incurred for work performed upto the reporting date, Rs. 100 of standard materials stored at the site for use in year 3.

The amounts of revenue, expenses and profit recognised in the statement of profit and loss in the three years are as follows:

Upto the Reporting Date Recognised in prior years Recognised in current year
Year 1
Revenue (9,000x .26) 2,340 - 2,340
Expenses (8,050x .26) 2,093 - 2,093
Profit 247 - 247
Year 2
Revenue (9,200 x .74) 6,808 2,340 4,468
Expenses (8,200 x .74) 6,068 2,093 3,975
Profit 740 247 493
Year 3
Revenue (9,200 x 1.00) 9,200 6,808 2,392
Expenses 8,200 6,068 2,132
Profit 1,000 740 260

Contract Disclosures

A contractor has reached the end of its first year of operations. All its contract costs incurred have been paid for in cash and all its progress billings and advances have been received in cash. Contract costs incurred for contracts B, C and E include the cost of materials that have been purchased for the contract but which have not been used in contract performance upto the reporting date. For contracts B, C and E, the customers have made advances to the contractor for work not yet performed.

The status of its five contracts in progress at the end of year 1 is as follows:

Contract

(amount in Rs. lakhs)
A B C D E Total
Contract Revenue recognised accordance with paragraph 21 145 520 380 200 55 1,300
Contract Expenses recognised in accordance with paragraph 21 110 450 350 250 55 1,215
Expected Losses recognised in accordance with paragraph 35 - - - 40 30 70
Recognised profits less recognised losses 35 70 30 (90) (30) 15
Contract Costs incurred in the period 110 510 450 250 100 1,420
Contract Costs incurred recognised as contract expenses in the period in accordance with paragraph 21 110 450 350 250 55 1,215
Contract Costs that relate to future activity recognised as an asset in accordance with paragraph 26 - 60 100 - 45 205
Contract Revenue (see above) 145 520 380 200 55 1,300
Progress Billings (paragraph 40) 100 520 380 180 55 1,235
Unbilled Contract Revenue 45 - - 20 - 65
Advances (paragraph 40) - 80 20 - 25 125

The amounts to be disclosed in accordancewith the Standard are as follows:

Contract revenue recognised as revenue in the period [paragraph 38(a)] 1,300
Contract costs incurred and recognised profits (less recognised losses) upto the reporting date [paragraph 39(a)] 1,435
Advances received [paragraph 39(b)] 125
Gross amount due from customers for contract work- presented as an asset in accordance with paragraph 41(a) 220
Gross amount due to customers for contract work- presented as a liability in accordance with paragraph 41(b) (20)
The amounts to be disclosed in accordance with paragraphs 39(a), 41(a) and 41(b) are calculated as follows:
(amount in Rs. lakhs)
A B C D E Total
Contract Costs incurred 110 510 450 250 100 1,420
Recognised profits less recognised losses 35 70 30 (90) (30) 15
145 580 480 160 70 1,435
Progress billings 100 520 380 180 55 5 1,235
Due from customers 45 60 100 - 15 220
Due from customers - - - 20 - (20)

The amount disclosed in accordance with paragraph 39(a) is the same as the amount for the current period because the disclosures relate to the first year of operation.

Footnotes

*Originally issued in December 1983 and titled as ‘Accounting for Construction Contracts’. The Standard was revised in 2002 and came into effect in respect of all contracts entered into during accounting periods commencing on or after 1-4-2003 and is mandatory in nature from that date. Accordingly, Accounting Standard (AS) 7, ‘Accounting for Construction Contracts’, issued by the Institute in December 1983, is not applicable in respect of such contracts.

#The Standard was earlier notified as part of Companies (Accounting Standards) Rules, 2006, under Companies Act, 1956. The Standard has been notified as part of Companies (Accounting Standards) Rules, 2021, under Companies Act, 2013. The Ministry of Corporate Affairs, Government of India, inserted the following footnote in Companies (Accounting Standards) Rules, 2021, which is relevant for companies:

“In respect of contracts entered into prior to the effective date of the notification prescribing Accounting Standard (AS) 7 as part of Companies (Accounting Standards) Rules, 2006, the applicability of this Standard would be determined on the basis of the Accounting Standard (AS) 7, revised by the ICAI in 2002.” (Please refer footnote * above)

1Attention is specifically drawn to paragraph 4.3 of the Preface, according to which Accounting Standards are intended to apply only to items which are material

2All paragraphs of AS 4 that deal with contingencies are applicable only to the extent not covered by other Accounting Standards prescribed by the Central Government. For example, the impairment of financial assets such as impairment of receivables (commonly known as provision for bad and doubtful debts) is governed by AS 4.